A bespoke digital tool was developed to provide real time insight into the progress of cable and system installation work. Project managers and engineers can now steer more effectively on status, bottlenecks and efficiency.
Milestones
5
Approach
Fixed price, phased delivery
Validation
Tested on 2+ projects
RH Marine is a leading supplier of maritime systems and electrical installations for the defence, offshore and shipbuilding sectors. The organisation manages complex projects in which dozens of cable and system installations run simultaneously, spread across multiple spaces and systems on board vessels.
Keeping track of progress across all of those workstreams was a real challenge. Project managers and engineers needed a way to see at a glance where each project stood, where delays were emerging, and how efficiently work was being carried out per compartment.
The challenge
There was no structured, visual way to translate installation data into actionable steering information. The underlying data existed, but not in a form that supported day to day project monitoring and decision making.
Blackbear's role
Blackbear helped sharpen the brief and translate the need into a concrete assignment. A specialist was selected with demonstrable experience in both software development and project management within technical environments. The assignment was structured as a fixed price engagement with clear milestones and a clearly defined end result, allowing RH Marine to steer on outcomes rather than hours and keep control over the process.
Result
A fully functional visualisation tool was delivered, making the progress of cable and wire connections per compartment visible through dynamic, colour coded dashboards and efficiency analysis. The tool was successfully validated against existing project data and includes export functionality for client facing reporting. Project managers now have a concrete instrument that supports faster, better informed decision making throughout the project lifecycle.